The accessibility project continues to make progress. As of last week, we were waiting for a second inspection of the electrical work. Once that passes, the framing can be inspected, and after that passes, we can have drywall! The plumbing has already passed inspection.
The top photo shows the framing and some of the electrical behind the door that leads into the new restroom space. At right is the plumbing and framing along the wall that will divide the men's and women's restrooms. A window in this former classroom straddles the new wall and will be bricked over.
Down the hall in the kitchen- ette, all is ready for the next phase. Pipes are ready for the sink, electrical outlets are in place for the stove and new refrigerator. All that is needed for carpentry and installation of the cabinets are those inspections!
An unexpected glitch was the need to install a new cutoff valve for the main water supply. As you can see, that ditch from a few weeks back has now been replaced with this clearly marked valve by the education building door.
We expect the contractor who will do the front entrance work to be available near the end of October. We are all hoping for a mild winter!
Please visit the sidebar articles about our financial progress, both from pledges and contributions as well as from fundraising. GoodShop is really taking off! You can painlessly donate $1.00 to Compton Cares by making 100 web searches on GoodSearch. Or, you can go through GoodShop for an online purchase and spend $100 with a merchant that donates 1%, or $34 with a merchant that donates 3%, or $20 with a merchant that donates 5%. Your cost is the same, but that $1.00 comes to Compton Cares. Just a thought as the holiday shopping season draws near. Thank you, everyone, for your support, your interest, your prayers for this project. We will publish updates here weekly, or when new developments take place.